Working closely with LM Manufacturing and Bedrock Detroit, Premier Construction & Design fully leveraged our integrated project delivery process to complete this very time sensitive project in less than a year from concept to completion!  Design and Construction work included the renovation over 265,000 SF of existing manufacturing/warehousing space and the new construction of a 33,000 SF addition connecting the existing facilities.  Premier’s fully integrated design, engineering, and construction solution included the following work:

  • Fully developed design including all required certifications and permits
  • Upgrade of fire suppression systems to ESFR
  • Ceiling (30’) to floor repaint of entire facility including color coding
  • Complete floor refinishing including epoxy and clear coating systems
  • Complete demolition, rework and rebuild of production floor restrooms
  • Troubleshooting and replacing components for 20 truck docks and wells and 40 entrances/exits 
  • Complete renovation of 21,000 square feet of offices including:
    • Bathrooms
    • Kitchen/break areas
    • Conference/huddle areas
    • Server rooms with specialty fire suppression
    • Private and Open office areas
  • Renovation of Cafeteria 
  • Build out of Quality control laboratories 
  • Extensive site work including
    • New pedestrian, passenger and truck entrances 
    • Complete mill/repave/striping of all parking areas
    • New underground storm water retention
    • New concrete curbs, walks, and paving for production area truck turning, parking and security required for quick production turnaround times
  • Upgraded exterior and interior lighting and controls

As a joint venture between LM Manufacturing and Magna International, this project was a part of the push to bring automotive manufacturing back into the city of Detroit and Premier couldn’t be more honored to have been a part of the team to make it happen! 

Detroit, MI